Sidewalk Improvement Project

Construction Information:  Scheduled for the weeks of April 9 through Mid-May.     

Next Scheduled Information Update: May 30, 2018 

Road Closure Information:  No road closures will occur during sidewalk project.

Important Additional Information:  Work on sidewalk construction from The Marriot Alley south to the alley in the 400 Block, South side of Kelly Ave from Cache to Jackson Street commenced April 9th. No interruption of traffic will occur during this construction project where this is new sidewalk construction. The Zero to 100 block of West Kelly Ave between Cache and Glenwood will have disruptions where existing sidewalk will be replace by the Baptize Church.  

Residences and business will have access during this project, however, access may be limited at times due to construction activities. Please plan accordingly. Construction work hours will be from 7:00 am to 7:00 pm.

For your safety and the safety of construction workers, please be aware of, and obey all construction notification, detour and parking restriction signage.

Please contact: Jeremy Parker (jparker@jacksonwy.gov ), Associate Engineer, Town of Jackson Public Works Department, with any questions, concerns, or comments regarding this project. If you are a resident of Snow King Drive or would like to be included in the Town’s construction notification contact list for the project, please email with your name, address, and phone number.

The 2018 Sidewalk Improvement Project will connect the corridors of South Cache Street and South Millward Street along the south side of West Kelly Avenue, in addition to completing sidewalk on South Millward Street to fill the gap between the new Marriott Hotel and the St. John’s Apartment Building.

Weather permitting, the project is scheduled to be completed between April 2nd and June 8th, 2018.  Construction hours will be Monday through Friday between the hours of 7:00am and 7:00pm.  This project may cause some traffic disruption as well as parking closures as sidewalks are being built.  

The project generally consists of constructing approximately 9,000 square feet of concrete sidewalk, approximately 580 lineal feet of curb and gutter, alleyway and driveway approaches, ADA ramps, associated crushed base, 720 square feet of concrete pavers, 20 cubic yards of top soil, 1,300 lineal feet dry utility trenching, street lights, electrical system tie in, and asphalt street patching.

Image of Sidewalk Improvements Plan

For your safety and the safety of construction workers, please be aware of, and obey all construction notification, detour and parking restriction signage.