Public Works Right of Way Capital Projects 2021

Meadowlark and Simpson Sidewalks

Synopsis/Purpose

Funded by 2017 SPET for Town of Jackson Pedestrian Improvements.  This SPET item is for the purpose of planning, design, engineering, and construction of pedestrian improvements including sidewalks, crosswalks, and ADA facilities within the Town of Jackson.  The project includes constructing sidewalks in three locations:

  1. Meadowlark Lane near South Highway 89
  2. East Simpson Ave between S Cache St and S Willow St
  3. Alley on S Willow Street between E Simpson Ave and E Hansen Ave

Dates

April through June 2021

Meadow1
meado2
MEadow3

Spring Patching and Crack Sealing

Synopsis/Purpose

The Town repairs spots on streets each spring and fall to address locations that are deteriorating, typically due to seasonal freeze-thaw cycles and aging road surfaces.  Patching and crack sealing help extend the useful life of road segments between resurfacing or reconstruction efforts to reduce overall costs to maintain them. 

Dates

April 15-May 29, 2021

In total, 25,071 square feet of patching is scheduled for the spring of 2021.  Locations of these patching projects include:

  1. Cache Creek Drive
  2. High School Road
  3. Rangeview Drive
  4. Corner Creek Lane
  5. Whitehouse Drive & South Park Loop
  6. South Millward
  7. North Glenwood
  8. Moran Street
  9. East Gill Avenue
  10. East Broadway
  11. West Karns
  12. S. Jackson Street
  13. Powderhorn Lane
  14. Buffalo Way
  15. Snow King Avenue

Cache Creek Tube Phase 2D

Synopsis/Purpose

The entire Cache Creek Tube project consists of removing and replacing 3,350 LF of a very eclectic, old, and obsolete collection and conveyance system of Cache Creek and stormwater drainage entering it.  Phase 2D of the Cache Creek Tube extends the section of Tube along Bruun Blvd (N Willow St) into Broadway to connect with the existing storm drainage system where a section of Tube in Bruun Blvd and improved drainage infrastructure in Broadway were constructed last summer.  In this Phase the Town will also install a new stormwater treatment unit at this location.   The treatment unit will be partially paid for by a WY DEQ grant.

Dates

April through June 2021

Cache

Well 9 Exploration

Synopsis/Purpose

The Town of Jackson’s water supply system includes three zones.  Zone 3 serves west Jackson and currently the system produces just enough water to meet demand during peak summer usage.  The Town is exploring Rangeview Park as a possible location for a new water supply well (Well 9).  The new well will help ensure enough water supply for firefighting during the peak demand periods and will provide for future demand in conjunction with a new Zone 3 water tank project, which is also currently undergoing feasibility analysis.   This project is funded by a Groundwater Exploration Grant from the WY Water Development Commission.

Dates

Mid-April through mid-June 2021

Test

Cache Creek Dr Sewer

Synopsis/Purpose

The project involves upgrading approximately 1,160 linear feet of sanitary sewer mains.  The old mains are vitrified clay tile and will be replaced with PVC pipes.  Construction staging for the project will be in the public right-of-way on the south side of Cache Creek Dr and west side of Redmond St.  This project is funded by the Wastewater Enterprise.

Dates

April-October 2021

Sewer

Chip Sealing

Synopsis/Purpose

The Town’s chip seal program helps to provide a well-maintained roadway network at an affordable cost.  Chip sealing creates a durable street surface and extends its useful life so that larger road resurfacing and reconstruction projects occur less frequently.  

Dates

August through mid-October, 2021

Sewer at Snow King Ballfield and Parking

Synopsis/Purpose

A portion of this sewer line will be replaced as part of the Snow King Gondola Construction.  This project involves the immediate downstream section of pipe, which needs to be upgraded to a larger size and steeper slope to improve flow.  The Town is aligning this project with the major construction taking place at Snow King to reduce disturbance in the area.

Dates

September through October 2021