Town of Jackson - Construction Project
Updates
May 5, 2020
CENTER STREET WATER MAIN REPLACEMENT
Location:
Center Street between Broadway and Gill
Construction Information:
The Town of Jackson and Westwood Curtis continue construction of the Center Street Water Main Replacement Project.
Concrete work along the curb line and pavement preparations will keep the roads closed for construction next week.
Pending cooperating weather, we’re scheduled to have pavement installed mid-May.
Schedule: (Weather Permitting)
*The Center Street / Deloney Intersection remains open for east-bound traffic.
*Center Street remains closed from Broadway to Gill.
*Paving week of May 11th (weather permitting).

CACHE CREEK TUBE STORMWATER PROJECT (Phase 2C)
Location:
Deloney and Willow
Construction Information:
The Town of Jackson and Westwood Curtis continue construction of the Cache Creek Tube Stormwater Phase 2C Project.
This project involves re-alignment of the Cache Creek stormwater piping into the Town’s right-of-way.
* Bruun St. (aka Willow) between Broadway and Deloney remain closed.
* Deloney between King and Willow remain closed.
* The Bus Stop is one block east of the regular START Bus Stop during this construction project.
Schedule: (Weather Permitting)
- Paving Planned for Deloney the week of May 18th.
- Paving Planned for Bruun the week of June 1st.
- Work hours are weekdays, 7:00 am to 7:00 pm.
- No construction work is planned on weekends.

2020 SIDEWALKS - JACKSON STREET
Location:
Jackson Street between Pearl Avenue and Broadway, and Pearl Avenue at the Jackson Street intersection
Construction Information:
The Town of Jackson and Evans Construction continue construction of the Jackson Street Sidewalk Project.
Roadway and curb and gutter construction work in the intersection of Pearl Avenue and Jackson Street and along Pearl Avenue will keep the intersection closed in all directions for approximately one week, starting May 5.
The block of Jackson St between Pearl Ave and Broadway will remain closed for continued roadway and sidewalk work until the end of May.
Schedule: (Weather Permitting)
- The Pearl Ave / Jackson St intersection will be closed to traffic in all directions May 5 through May 11.
- Jackson Street remains closed from Pearl Ave to Broadway until the end of May.